CEs | 16 | AEs | 219 |
SEs | 77 | JEs | 113 |
EEs | 167 | Accounts staff | 104 |
AEEs | 219 | Contractors' staff | 23 |
STA | 13 | ||
Total of 907 personnel trained in four years |
Year | Peri od of Train ing/ Work shop | Training Course | Training Centre | Nos. of Trainees | |||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
JE | AE | AEE | EE | SE | CE/ Addl. CE | Accounts Staff | Contracto rs/ Contractor 's Staff | STA | Total | ||||
2013 | 4-9 March | DPR Preparation | ARR&TI | 10 | 18 | 17 | 2 | 1 | 48 | ||||
18-19 July | Contract Management | ARR&TI | 6 | 11 | 8 | 6 | 31 | ||||||
30 Sept | Environmental & Social safeguard | ARR&TI | 6 | 12 | 14 | 9 | 2 | 43 | |||||
28-31 Oct | Total Station Survey | ARR&TI | 20 | 20 | |||||||||
30-31 Dec | DPR Preparation/Quality Control & Quality Assurance | ARR&TI | 21 | 20 | 41 | ||||||||
2014 | 26 Feb | Bridge Design | ARR&TI | 16 | 3 | 2 | 21 | ||||||
27 Feb | Routine Maintenance | ARR&TI | 5 | 10 | 8 | 21 | 8 | 2 | 54 | ||||
9-10 June | Essential Contract Management | ARR&TI | 4 | 4 | 10 | 16 | 2 | 36 | |||||
13-14 June | OMMAS New Versiomn | ARR&TI | 7 | 9 | 3 | 6 | 43 | 68 | |||||
23 June | Asset management | ARR&TI | 8 | 7 | 19 | 14 | 11 | 1 | 60 | ||||
24-26 June | Road Safety | ARR&TI | 12 | 12 | 16 | 12 | 5 | 1 | 58 | ||||
27 June | OMMAS New Versiomn | ARR&TI | 27 | 21 | 5 | 61 | 114 | ||||||
26-29 Aug | Road Safety & Contract management | ARR&TI | 5 | 6 | 10 | 5 | 1 | 27 | |||||
4-5 Sept | Contract Management | ARR&TI | 1 | 8 | 13 | 12 | 3 | 2 | 8 | 47 | |||
8-13 Sept | Project Management | ARR&TI | 4 | 4 | 18 | 5 | 31 | ||||||
22-26 Sept | Inventory & Road Surface Condition Survey and Traffic Road Survey | ARR&TI | 5 | 5 | 6 | 1 | 1 | 18 | |||||
14-15 Oct | Contract Issues & its resolution | ARR&TI | 4 | 1 | 4 | 1 | 1 | 15 | 26 | ||||
2-3 Dec | Workshop on New Materials/Technologies for Rural Roads on 2nd & 3rd December, | ARR&TI | 2 | 5 | 1 | 6 | 6 | 6 | 14 | 40 | |||
2015 | 27Jan - 01 | Project Management | ARR&TI | 3 | 3 | 9 | 4 | 19 | |||||
27-28 Feb. | New Technologies on Environmentally Optimized | ARR&TI | 8 | 11 | 9 | 2 | 30 | ||||||
18 - 22 May | Social & Environmental Safeguard | I.I.E.,NH- | 4 | 10 | 5 | 3 | 1 | 23 | |||||
7-12 Sept | Project Management | "The Lily Hotel" | 1 | 8 | 8 | 1 | 18 | ||||||
23-24 Sept | Contract Management | The Lily Hotel | 8 | 2 | 7 | 4 | 21 | ||||||
2016 | 4-9 Jan | Project Management | I.I.Engg, Panbaza | 2 | 10 | 1 | 13 | ||||||
113 | 219 | 174 | 16 | 77 | 16 | 104 | 23 | 27 |
Sl. No. | Year | Numbers of training programmes organized during the year |
---|---|---|
1 | 2013 | 5 |
2 | 2014 | 13 |
3 | 2015 | 5 |
4 | 2016 | 1 |
5 | 2017 (proposed) | 9 |
TOTAL | 33 |